Skip to main content

Variable on Welding procedure specification (WPS) Refer to ASME sec IX

 

Welding procedure specification (WPS) ASME sec IX

A welding procedure specification is a written document providing direction to the welder (or welding operator). It contains all the necessary parameters viz. joints, base metals, filler metals, positions, preheat, PWHT, gas etc. (including ranges, if any) under which the welding process must be performed. These parameters are known as variables (as per ASME Section IX). Three types of variables are mentioned in the code, these are;

  1. Essential Variable
  2. Non essential Variable
  3. Supplementary Essential variable

Essential Variables (For WPS – QG-105.1 & QW-251.2): A change in essential variable is considered to affect the mechanical properties (other than toughness) of the welded joint. Hence the WPS must be requalified, if the essential variable is changed.

Note: QG-105.2 is for Welder.

8.PNG

10

Supplementary Essential Variables (QG-105.3 & QW-401.1): A change in the supplementary essential variable will affect the toughness properties of the joint, heat-affected zone, or base material. Hence supplementary essential variables become additional essential variables in situations where procedure qualification requires toughness testing. When procedure qualification does not require the addition of toughness testing, supplementary essential variables are not applicable.

12.PNG

13.PNG

Nonessential Variables (QG-105.4 & QW-251.3): Nonessential variables are those in which a change can be made without requalification of the existing WPS, since it is not considered to affect the mechanical properties of the joint. Though a change in the nonessential variable doesn’t require requalification of the WPS but still it should be properly addressed in the welding procedure specification (WPS).

11.PNG

14.PNG

15.PNG

Comments

Popular posts from this blog

MILL TEST CERTIFICATE is...?

  A Mill Test Certificate (MTC), or Mill Test Report (MTR), is issued by a manufacturer to certify the chemical and mechanical features of a product and its compliance to the applicable norms and technical specifications. Typically, Mill Test Certificates conform to the EN 10204 standard and are related to steel products. MILL TEST CERTIFICATE A mill test certificate to EN 10204 shows, generally, the following information: Type of certificate and standard (example EN 10204 3.1 or EN 10204 3.2) Manufacturer name Product name and dimensions Quantity covered by the certificate (example: tons, with heat numbers) Heat numbers and batch number (physically shown on the product as well) Final test result Dimensional measurements, to check compliance with allowed tolerances (example, for steel pipes: diameter, wall thickness, length, straightness) Material grade and applicable specification, including results of chemical and mechanical tests Results of additional tests, like hydrostatic, ultras

PWHT EXEMPTION REQUIREMENTS IN ASME CODES

PWHT EXEMPTION REQUIREMENTS IN ASME CODES In order to guess the technical background on PWHT exemption, PWHT exemption requirements in several ASME codes are reviewed. ASME codes suggested that PWHT is not mandatory when the nominal material thickness is not more than the thickness in Table 1.   There was some variation between codes as shown in Table 1, and the reason for this has been not known. There are the general trends that the permitted thicknesses without PWHT is increased with increasing preheat temperature together with reductions in maximum carbon level, and the permitted thickness is decreased with increasing alloy content of steels. Most manufacturers are trying to avoid PWHT based on the Table 1 because there is an economic incentive to avoid PWHT.  REFERENCES   [1] Pingsha Dong and J.K.Hong, "Residual stress relief in post-weld heat treatment", 2008 ASME Pressure Vessels and Piping Conference, PVP2008-61210.  [2] ASME Section III, NX, "Rules for Construct

Storage Tank API 650 - Summary

Shop Fabrication Inspection 1         Material Receiving Inspection Report Ø       Check visual (free of lamination & damage). Ø       Check certificate (keaslian, Heat No & Plate No). Ø       Check dimensional (Length, Thickness, Width & Diameter). 2         Marking Ø       Check dimensional marking. Ø       Check transfer heat no. 3         After Cutting Ø       Check dimensional. Ø       Check traceability (Heat No & Plate No). Ø       Check Stamp Marking. 4         Rolling Ø       Check visual (free of damage). Ø       Check edge preparation. Ø       Check Rolling radius. 5         Painting Ø       Check material painting (batch no, self life, brand). Ø       Check Ambient Condition (surface & whether). Ø       Check DFT. Field Erection Inspection 6         Dimensional Inspection 1         Peaking banding Peaking measured using a horizontal sweep board 36 inch (900 mm) long. Tolerance of peaking shall not exceed